AN INVESTIGATION INTO DESIGN ERRORS AND IT IMPACT ON INITIAL COST OF A CONSTRUCTION PROJECT


AN INVESTIGATION INTO DESIGN ERRORS AND IT IMPACT ON THE INITIAL COST OF A CONSTRUCTION PROJECT    

ABSTRACT

This research project investigated the effects of design error on the final cost of a project in Nigeria. It is a key issue, because many projects in Nigeria have inadequacies in the plans and specifications which have been major causes of changes to the contract. There have been extreme examples of design errors such as numerous building collapses in Nigeria - projects that have wrought disaster after the construction are completed. One or two major errors that can be corrected with only initial cost considerations and little effect on the schedule finally ends up causing major impacts on the final cost and schedule growth. These dilemmas place an increasing pressure on stakeholders in the construction industry to search for solutions that will minimize error in designs so as to maintain estimated construction cost and time while maximizing its quality. One hundred and twenty selected project clients, consultants and contractors in Imo state of Nigeria were issued well structured questionnaires to elicit responses on the investigation of the effect of design error on the final cost of a project, and the analysis of data was done using pie chart. The research study revealed that design error affects final cost of a construction project causing cost overrun on cost and time. Additionally, the research revealed that the issue of cost and time impacts on project construction could be managed by using construction recognized and accepted methodologies which identifies and quantifies the overall impact to the project. The research concludes that unclear scope of work or change in scope of work; time and inexperience of the designer and inaccuracy of the design documents are the major causes of design error on construction projects in Nigeria. In this regard the paper recommends that the consultants’ experience, lack of design reviews, design management experience, awareness of changes in standards, communications and availability of information, inconsistent decision making, and lack of coordination between disciplines, lack of planning and inspection of project and unclear or ambiguous requirements for design specifications should be worked upon by the stakeholders concerned in order to prevent the occurrence of design error in construction projects in Nigeria.

TABLE OF CONTENTS

Content                                            Page

Title page    -    -    -    -    -    -    -    -    -    -    i

Approval    -    -    -    -    -    -    -    -    -    -    ii

Dedication    -    -    -    -    -    -    -    -    -    -    iii

Acknowledgement    -    -    -    -    -    -    -    -    -    iv

Abstract    -    -    -    -    -    -    -    -    -    -    v

CHAPTER ONE

INTRODUCTION

1.1 BACKGROUND OF THE STUDY

1.2 STATEMENT OF THE PROBLEM

1.3 AIM AND OBJECTIVES OF THE STUDY

1.3.1 AIM

1.3.2 OBJECTIVES

1.4    RESEARCH QUESTIONS

1.5 HYPOTHESIS FORMULATION

1.6 SIGNIFICANCE OF THE STUDY

1.7 SCOPE OF STUDY

1.8 LIMITATION OF THE STUDY

1.9 DEFINITION OF TERMS

CHAPTER TWO

2.0 LITERATURE REVIEW

2.1 INTRODUCTION

2.2 THEORETICAL FRAMEWORK

2.3 THE NIGERIAN CONSTRUCTION INDUSTRY

2.4 CONCEPT OF CONSTRUCTION PROJECT

2.4.1 CONSTRUCTION PROJECT

2.4.2 BUILDING CONSTRUCTION PROJECT

2.5 CLIENTS IN BUILDING CONSTRUCTION PROJECT

2.6 PARTIES IN A BUILDING CONSTRUCTION PROJECT

2.7 ERRORS IN BUILDING CONSTRUCTION PROJECTS   

2.8RESPONSIBILITY FOR ERRORS

2.9 SOURCES OF CHANGES IN PROJECT BUDGET

2.10 FACTORS THAT CONTROL DESIGNS AND

CONSTRUCTION

2.11 EFFECT OF DESIGN ERRORS ON A PROJECT  

2.12 MINIMIZING FINAL CONSTRUCTION COST

2.13 CHAPTER SUMMARY

CHAPTER THREE

RESEARCH METHODOLOGY

3.1 INTRODUCTION

1.2    RESEARCH DESIGN

1.3    STUDY AREA

1.4    SAMPLING DESIGN AND PROCEDURES

1.5    DATA COLLECTION INSTRUMENT

3.6 ADMINISTRATION OF THE DATA COLLECTION

INSTRUMENT

3.7 DATA PRESENTATION

3.8 STATISTICAL TOOLS FOR DATA ANALYSES

CHAPTER FOUR

DATA PRESENTATION, ANALYSES, INTERPRETATION AND DISCUSSION OF FINDINGS

4.1 INTRODUCTION

4.2 DATA PRESENTATION

4.3 DATA ANALYSIS

HYPOTHESIS TESTING

4.4 DISCUSSION OF FINDINGS

CHAPTER FIVE

5.0 CONCLUSION AND RECOMMENDATION

5.1 CONCLUSION

5.2 RECOMMENDATION

REFERENCES

APPENDIX I

RESEARCH QUESTIONNAIRE

CHAPTER ONE

INTRODUCTION

1.1 BACKGROUND OF THE STUDY

When asked to define "design error," not all disciplines in the construction process agree on a common definition. Depending on which discipline you address, the owner, the designer or the contractor, there will be a common understanding surrounded by varied conclusions, "a mistake." From the basic definitions of "design" and "error" we conclude that a design error is a deviation from a drawing or specification, also including omissions and ambiguities. It is the seriousness of this error that must be considered to determine its consequences on the overall outcome of the project. One of the most important challenges facing management today is controlling the ball too frequent final cost and schedule overruns that effect the construction industry (Diekmann and Thrush, 1986). One of the major issues to control growth in project final costs and time is the reduction of design errors.

The owner, designer and contractor all have different interests in, or uses for the design of a facility. But what they do share is the commitment to complete the project safely and within a given budget and completion time. There are many initiatives being conducted to control the growth of final cost and schedule within the construction industry.

The major issue is "accuracy of the drawings," or the number of design errors, omissions and ambiguities within the plans and specifications that affect the quality of the facility. Inadequacies in the plans and specifications are the major causes of changes to the contract So much emphasis is placed on the issue of time and final cost that quality takes a back seat .The quality of the project depends on the conformance of the objectives and requirements from the owner. An informative quality management technique will provide an agreement to procedures and definitions among the principle parties for the project. Since design errors have an impact on the outcome of the effectiveness of the contractor's effort on the project it is essential that all parties determine what the definition of a design error should be.

1.2 STATEMENT OF THE PROBLEM

Design errors indicate the total design in-effectiveness of a project. Major design quality problems occur during construction when errors, omissions and ambiguities in plans and specifications become evident (Davis and Ledbetter, 1987). This statement directs that the inadequacies in the plans and specifications are the major causes of changes to the contract. There have been extreme examples of design errors such as numerous building collapses in Nigeria - projects that have wrought disaster after the construction are completed. These are examples of design errors that escaped the close scrutiny of all parties. One or two major errors that can be corrected with only initial cost considerations and little effect on the schedule can impact projects. The projects that really suffer are those with many small errors (design, rework or change of scope) which when finally added up causes major impacts on the final cost and schedule growth. Through Davis and Ledbetters research it was determined that "accuracy of the design documents" was the most critical of the criteria used in the initial evaluation of design effectiveness. This accuracy was further described as the concern for the frequency and impact of errors in the specifications and drawings. This is due to the fact that the drawings and specifications are the most "readily identifiable outputs of the design process." It is even more important that the quality control of designs be addressed during the planning phase and closely monitored during the construction phase.

Design errors of a project have been an issue that has been misconstrued. The attitude towards design errors in the country can now be best described as tardy and unsatisfactory.

1.3 AIM AND OBJECTIVES OF THE STUDY

1.3.1 AIM

The main aim of the study is to investigate how design errors can affect the final cost of a project.

1.3.2 OBJECTIVES

The specific objectives are:

1.    To determine what constitutes a design error.

2.    To examine the contributing factors to design errors in Nigeria.

3.    To examine how these factors can affect final cost of a project.

4.    To proffer solutions on how to minimise cost of construction projects in Nigeria.

1.4    RESEARCH QUESTIONS

1.    What are design errors in construction projects?

2.    What makes or contributes to a design error?

3.    What are the factors that lead to design errors?

4.    What effect can design errors have on final cost and growth of a project?

5.    Who is responsible for design error?

1.5 HYPOTHESIS FORMULATION

1. H0: Design error affect final cost of a building construction project.

H1: Design error does not affect final cost of a building construction project.

2. H0: Design errors causescost overrun in a building construction project.

H1: Design errors does not causecost overrun in a building construction project.

3. H0: Additional work causes additional cost in a building construction project due to design errors.

H1: Additional work does not cause additional cost in a building construction project due to design errors.

1.6 SIGNIFICANCE OF THE STUDY

This study gives a clear insight into the various ways in which contractors in the construction companies in Nigeria can maximise profits and reduce final cost through effective and efficient contract planning and management. The study also gives a clear insight into the various effects of design errors on the final cost of a project. The findings and recommendations of the researcher will help in building a strong and better project management guideline for contractors in Nigeria.

Also, the study of the investigation of the effect of design errors on the final cost of a project will provide results that will offer the following benefits:

1.    Establish the scope and methodology of design functions performed by Architectural firms for the benefit of the entire construction industry including prospective building clients.

2.    Assist designers in understanding the cost implication of design errors, so that they can make objective design decisions during the early phase of a project.

3.    Avail the designer with a tool for eradicating errors that are directly related to the designer that delay and or add cost to the project.

1.7 SCOPE OF STUDY

The study is on the investigation of the effect of design errors on the final cost of a project. It is narrowed down to building construction projects in Imo state of Nigeria.

1.8 LIMITATION OF THE STUDY

The only limitation faced by the researcher in the course of carrying out this study was the delay in getting data from the various respondents. Most respondents were reluctant in filling questionnaires administered to them due to their busy schedules and nature of their work. The researcher found it difficult to collect responses from the various respondents, and this almost hampered the success of this study.

1.9 DEFINITION OF TERMS

⦁    Design: The basic definition of design, according to Webster, is "the making of drawings or plans to plan and fashion the form and structure of an object to have intentions or purposes." The quality of planning and design is one of the primary factors of success in any project endeavour (Chalabi, Beaudin and Salazar, 1987). The design includes every aspect of the facility construction including operation and maintenance. The design incorporates a set of specifications to guide the contractor in developing his means and methods of construction.

⦁    Error: An error is defined, according to Webster, as "a deviation from accuracy or correctness; a mistake, as in action or procedure; an inaccuracy, as in speaking or writing." There are basically three types of errors: imperfections, non-conformance and omissions. Imperfections are deviations in details that have no affect on the assembly or facility (Davis and Ledbetter, 1987).

⦁    Design Error: From the evaluation above a simple definition of design error is "a deviation from the plans and specifications." It is not the intention of this definition to include any final cost or schedule growth or insinuate its root causes or legal responsibility. It is the responsibility of the owner, designer and contractor to establish the criteria in order to make a reasonable determination for responsibility. The survey shows a common theme, that of a mistake or error in the design. The survey also indicates several reasons why design errors exist and who cause them. This provides evidence that there is not a concise definition within the construction industry.

⦁    Contract:  Erikson (2002) defined Contract as an agreement that creates an obligation binding upon the parties thereto. The essentials of a contract are as follows: (1) mutual assent; (2) a legal consideration, which in most instances need not be pecuniary; (3) parties who have legal capacity to make a contract; (4) absence of fraud or duress; and (5) a subject matter that is not illegal or against public policy.

⦁    Contract Planning: According to Simmons (2007),Contract planning is the process of systematically and efficiently managing contract creation, execution and analysis for maximising operational and financial performance and minimising risk.

⦁    Contractor: ⦁    General contractor, organization or individual that contracts with another organization or individual (the owner) for the construction of a building, road or other facility.

⦁    Profit:  Tucy (2008) defined profit as the difference between the purchase price and the initial costs of bringing to market.

⦁    Final Cost: final costare not fixed, expenses incurred on the purchase of ⦁    land, ⦁    buildings, ⦁    construction, and equipment used in the production of ⦁    goods or in the rendering of ⦁    services. Put simply, it is the total final cost used to bring a project to a commercially operable status.

.

AN INVESTIGATION INTO DESIGN ERRORS AND IT IMPACT ON INITIAL COST OF A CONSTRUCTION PROJECT



TYPE IN YOUR TOPIC AND CLICK SEARCH.






RESEARCHWAP.NET

Researchwap.net is an online repository for free project topics and research materials, articles and custom writing of research works. We’re an online resource centre that provides a vast database for students to access numerous research project topics and materials. Researchwap.net guides and assist Postgraduate, Undergraduate and Final Year Students with well researched and quality project topics, topic ideas, research guides and project materials. We’re reliable and trustworthy, and we really understand what is called “time factor”, that is why we’ve simplified the process so that students can get their research projects ready on time. Our platform provides more educational services, such as hiring a writer, research analysis, and software for computer science research and we also seriously adhere to a timely delivery.

TESTIMONIES FROM OUR CLIENTS


Please feel free to carefully review some written and captured responses from our satisfied clients.

  • "Exceptionally outstanding. Highly recommend for all who wish to have effective and excellent project defence. Easily Accessable, Affordable, Effective and effective."

    Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.
  • "I saw this website on facebook page and I did not even bother since I was in a hurry to complete my project. But I am totally amazed that when I visited the website and saw the topic I was looking for and I decided to give a try and now I have received it within an hour after ordering the material. Am grateful guys!"

    Hilary Yusuf, United States International University Africa, Nairobi, Kenya.
  • "Researchwap.net is a website I recommend to all student and researchers within and outside the country. The web owners are doing great job and I appreciate them for that. Once again, thank you very much "researchwap.net" and God bless you and your business! ."

    Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.
  • "Great User Experience, Nice flows and Superb functionalities.The app is indeed a great tech innovation for greasing the wheels of final year, research and other pedagogical related project works. A trial would definitely convince you."

    Lamilare Valentine, Kwame Nkrumah University, Kumasi, Ghana.
  • "I love what you guys are doing, your material guided me well through my research. Thank you for helping me achieve academic success."

    Sampson, University of Nigeria, Nsukka.
  • "researchwap.com is God-sent! I got good grades in my seminar and project with the help of your service, thank you soooooo much."

    Cynthia, Akwa Ibom State University .
  • "Sorry, it was in my spam folder all along, I should have looked it up properly first. Please keep up the good work, your team is quite commited. Am grateful...I will certainly refer my friends too."

    Elizabeth, Obafemi Awolowo University
  • "Am happy the defense went well, thanks to your articles. I may not be able to express how grateful I am for all your assistance, but on my honour, I owe you guys a good number of referrals. Thank you once again."

    Ali Olanrewaju, Lagos State University.
  • "My Dear Researchwap, initially I never believed one can actually do honest business transactions with Nigerians online until i stumbled into your website. You have broken a new legacy of record as far as am concerned. Keep up the good work!"

    Willie Ekereobong, University of Port Harcourt.
  • "WOW, SO IT'S TRUE??!! I can't believe I got this quality work for just 3k...I thought it was scam ooo. I wouldn't mind if it goes for over 5k, its worth it. Thank you!"

    Theressa, Igbinedion University.
  • "I did not see my project topic on your website so I decided to call your customer care number, the attention I got was epic! I got help from the beginning to the end of my project in just 3 days, they even taught me how to defend my project and I got a 'B' at the end. Thank you so much researchwap.com, infact, I owe my graduating well today to you guys...."

    Joseph, Abia state Polytechnic.
  • "My friend told me about ResearchWap website, I doubted her until I saw her receive her full project in less than 15 miniutes, I tried mine too and got it same, right now, am telling everyone in my school about researchwap.com, no one has to suffer any more writing their project. Thank you for making life easy for me and my fellow students... Keep up the good work"

    Christiana, Landmark University .
  • "I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!."

    Musa, Federal University of Technology Minna
  • "I was scared at first when I saw your website but I decided to risk my last 3k and surprisingly I got my complete project in my email box instantly. This is so nice!!!."

    Ali Obafemi, Ibrahim Badamasi Babangida University, Niger State.
  • To contribute to our success story, send us a feedback or please kindly call 2348037664978.
    Then your comment and contact will be published here also with your consent.

    Thank you for choosing researchwap.com.